Module 4 of 10

Contracts and consultants

Module 4 covers Folder 02, Contracts and MOUs, which holds the signed agreements with contractors, consultants, and partners and the records that support them. You will finish with a complete file for each agreement, a check of its dates, and a list of the agreements that require a lobbying certification.

  • Financial monitoring
  • For finance staff
  • 3 lessons
  • About 25 minutes
  • Guidebook pages 23 to 25

Key questions

  • What belongs in each contract file?
  • Which three dates does a monitor compare, and in what order should they fall?
  • What must every consultant agreement state?
  • When are a lobbying certification and an SF-LLL required?

Finance staff keep Folder 02. The procurement policy from Lesson 3.3 sets the rules, and the records in this folder show that each purchase followed them.

The examples in this series follow one made-up award, the Riverbend County Reentry Support Project, funded at $300,000. Every name, number, and record shown in an example is fictional.

Lesson 4.1The contract file

What the monitor looks for

Folder 02 holds the signed agreements with contractors, consultants, and partners, along with the procurement records, SAM.gov checks, and lobbying certifications that support them. The folder answers the requests for consultant agreements and lobbying certifications.

When a contract is missing, unsigned, or signed after the work began, all of the costs under it can be questioned, even when the work itself was done well.

Watch the dates

The three dates a monitor compares are the SAM.gov search, the contract signature, and the first day of service. They should fall in that order.

  1. SAM.gov searchDated before the contract was signed.
  2. Contract signatureSigned by both parties before services begin.
  3. First day of serviceWork starts after the agreement is in place.

A no-cost extension does not extend your agreements

Check every contract and MOU at least once a year to confirm that it has not expired. A no-cost extension lengthens the award, but it does not lengthen the agreements under the award, so each contract and MOU that will continue needs a signed amendment with a new end date before the current one passes.

The Grant Management Resources page explains how to request a Project Period Extension in JustGrants under Making Changes to Your Award.

What a good answer looks like

Contract file checklist

Example: checking an invoice against the contract (fictional)

CheckContract saysInvoice saysResult
Rate$40 per hour$40 per hourMatches
Service period12/1/2025 to 9/30/2026August 1 to 31, 2026Within the period
Hours or unitsUp to 225 hours18 hours, 171 used to dateWithin the limit
DeliverableQuarterly data summarySummary attachedDelivered
ApprovalProject directorApproved 9/6/2026Complete

Build it

Check the three dates for one agreement

Enter all three dates.

List every agreement and its end date

Contractor, consultant, or partnerEnd dateLast checkedAmendment needed

File milestone

Folder 02 holds a file for every contract and MOU. Each file has the signed agreement, the procurement record, and a SAM.gov search dated before the signature, and each end date has been checked.

Lesson 4.2Consultant agreements

What the monitor asks for

Be prepared to provide the following

If consultants are paid with grant funds, a copy of all agreements with individual consultants.

What a good answer looks like

Every individual consultant needs a signed agreement that was in place before the work began. Consultant rates are often capped at $650 a day unless you obtain prior approval, so check the rate in each agreement against your award and against Section 3.6, Costs Requiring Prior Approval, of the DOJ Grants Financial Guide.

Example: the Riverbend evaluator (fictional)

The Riverbend evaluator is an individual consultant. The agreement states the scope of work, which includes a quarterly data summary, a rate of $40 per hour for up to 225 hours, and a period of performance of 12/1/2025 to 9/30/2026. The invoice check in Lesson 4.1 compares the August 2026 invoice with those terms.

Build it

File milestone

Folder 02 holds a signed agreement for every individual consultant, and each rate has been checked against the award.

Lesson 4.3Lobbying certification and disclosure

What the monitor asks for

Be prepared to provide the following

If the award funded a contract, subcontract, or subaward at any tier over $100,000 in cumulative amount, copies of the contractor's, subcontractor's, or subrecipient's lobbying certification and disclosure of lobbying activities (SF-LLL).

What a good answer looks like

The threshold is cumulative and applies at any tier, so a contract that starts below $100,000 and is later amended above it comes into scope. Collect the certification at signing for any agreement that could reach the threshold.

Example: the Riverbend award (fictional)

The Riverbend budget includes $78,000 for subawards and $78,000 for procurement contracts, so no single agreement exceeds $100,000. This request does not apply to the Riverbend award.

Build it

Check an agreement against the threshold

Enter the original amount of the agreement.

File milestone

You have a list of every agreement over $100,000 cumulative, with a lobbying certification and an SF-LLL on file for each one, or a note that no agreement reaches the threshold.

Before you move onWhat Folder 02 should include

Check your understanding

Your award receives a no-cost extension. Are the contracts and MOUs under it extended too?

No. Each contract and MOU that will continue needs a signed amendment with a new end date before the current one passes.

In what order should the SAM.gov search, the contract signature, and the first day of service fall?

The SAM.gov search first, then the contract signature, then the first day of service.

A $90,000 contract is amended to $110,000. What is now required?

A lobbying certification and a disclosure of lobbying activities (SF-LLL). The threshold is cumulative, so the amended contract comes into scope.